Suciu Popa | Unlocking the offshore petroleum projects

31 August 2021   |   Cleopatra Leahu, Partner si Noemi Siman, Senior Associate - SUCIU POPA

The legislative process of the Project must be followed with great interest by all operators involved in the development of offshore petroleum projects, in order for the final form of the proposed provisions to correspond with the characteristics and nature of such works.

 
 
After almost 3 years from the enactment of Law no. 256/2018 on certain necessary measures for implementing petroleum operations by titleholders of petroleum agreements related to offshore petroleum blocks (“Offshore Law”), Romania takes another step for unblocking such projects. 

Although the Offshore Law established that the reception procedure would be regulated within 90 days as of the date of entry into force of the aforementioned piece of legislation, according to public available information, the lengthy consultations held between the Ministry of Energy and the Competent Authority for Regulating Petroleum Operations in the Black Sea (“ACROPO”) resulted in extended delays.

A first attempt in order to develop the legislative framework with regard to the reception procedure was initiated on 19 November 2020, when a Draft Government Decision was published on the website of the Ministry of Economy, Energy and Business.

After almost 1 year of passivity, on 27 August 2021, a new form of the reception procedure was published on the Ministry of Energy website, respectively the Draft Government Decision on the approval of the Procedure for the reception of works related to the petroleum operations conducted by the titleholders of petroleum agreements pursuant to Law no. 256/2018 on certain necessary measures for implementing petroleum operations by titleholders of petroleum agreements related to offshore petroleum blocks (the "Project").

In a nutshell, according to the Project, the reception of works represents a component of the quality system and is a complex process, which will certify, in accordance with the law, the completion of works performed under the Offshore Law. The provisions of the Project establish the following main aspects: (i) the organization of the reception procedure; and (ii) the allocation of responsibilities.

The participants within the reception procedure will be:

            (i)                 the titleholders of the authorization deed;


            (ii)               the contractor which performed the execution of the works;

            (iii)             the designer of the works;

            (iv)              the Independent Body/Independent Examination Entity chosen by the titleholder of the authorization deed;

            (v)                the representative (s) of the Ministry of Energy;

            (vi)              other competent institutions or specialists within the oil and natural gas field, as guests of the Ministry of Energy.

The Ministry of Energy shall be entitled to grant the final act of reception of the works executed further to the authorization deed.

The reception procedure shall be performed for all the works envisaged by the authorization deed, in accordance with the documentation based on which it was issued, and shall be admitted or rejected on motivated grounds. In case of rejection, the titleholders of the authorization deed shall have the obligation to remedy the ascertained problems and the reception procedure shall be re-performed with regard to the identified issues.

In order to fulfil the reception procedure, the Ministry of Energy and ACROPO shall each appoint one/two representatives, who shall be a part of the competent committee for: (i) analysing the reports prepared in accordance with the proposed provisions of the Project; and (ii) communicating to the titleholder of the authorization deed the document certifying the reception of works.

Unlike the draft of the reception procedure proposed in 2020, the Project does not contain any provision regarding the possibility of taking over a part of the works, during a certain physical stage of execution.

According to the public available information, the observations or suggestions with regard to the Project shall be submitted until 6 September 2021.

In this context, the legislative process of the Project must be followed with great interest by all operators involved in the development of offshore petroleum projects, in order for the final form of the proposed provisions to correspond with the characteristics and nature of such works.

Suciu Popa is a top law firm with a full-service practice, with notable performances within all areas of business law, including dispute resolution and arbitration, real estate, administrative disputes, project development, energy & renewables, being constantly ranked by all local and international directories in the top tiers of legal services providers. Fully committed to making a difference on the Romanian market, Suciu Popa relies on the solid experience and reputation of its attorneys and partners, built over more than 20 years of acting for multinational clients, strategic investors and investment funds, public authorities and international financial institutions, in some of the most complex cross-border transactions, investment projects and dispute resolution cases.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 2173 / 4698
 

Ascunde Reclama
BREAKING NEWS
ESENTIAL
Reff & Asociații | Deloitte Legal a asistat pro bono Asociația Tășuleasa Social în obținerea atestării Via Transilvanica drept traseu pedestru de interes național în scop recreativ
LegiTeam: MITEL & ASOCIATII caută Avocat care să se alăture echipei sale de Real Estate
NNDKP a asistat Carrefour în legătură cu finalizarea vânzării tuturor operațiunilor din România către Pavăl Holding. Echipa, coordonată de Partenerii Corina Dumitru (Corporate ̸ M&A) și Lavinia Ioniță Rasmussen (Tranzacții Imobiliare)
WTR Global Leaders 2026 | România urcă la 19 reprezentanți în liga mondială a specialiștilor în mărci – mai mulți decât Italia și aproape cât Franța. Ana-Maria Baciu (BACIU Partners), Sorina Olaru și Florina Firaru (NNDKP), Ciprian Dragomir (Țuca Zbârcea & Asociații) și Alina Tugearu (ZRVP) rămân în elita globală, iar lista se îmbogățește cu două nume de referință. Cine sunt avocații evidențiați, prin ce s-au remarcat și cum îi văd clienții
Filip & Company obține o victorie de referință într-un litigiu privind protecția construcțiilor învecinate. Proiect gestionat de Alin Grapă (Counsel) și Eduard Maxim (Senior Associate)
​​ZEISS a semnat achiziția EDY OPTIC și face pasul către operarea directă pe piața românească a opticii medicale. Schoenherr a fost consultantul cumpărătorului în această tranzacție
O tranzacție reper în zona finanțărilor din piața imobiliară: Kinstellar a asistat Deutsche Pfandbriefbank în refinanțarea de 123 mil. € a Radisson Blu (București). O altă firmă regională a stat alături de proprietarii complexului hotelier | Finanțare coordonată de la București, cu o echipă din mai multe jurisdicții și cu partenerii Magdalena Raducanu și Victor Constantinescu în prim plan
Reff & Asociații și Deloitte România au obținut o victorie definitivă într-un litigiu fiscal complex privind proprietatea intelectuală, serviciile intra-grup și prețurile de transfer. Ajustări de peste 90 de milioane de lei impuse de ANAF au fost anulate
Avocații firmei Bohâlțeanu și Asociații au stat alături de retailerul internațional SPAR, împreună cu Cerha Hempel, firmă cu alonjă regională, în vânzarea participației în rețeaua de magazine Hervis din România și Ungaria. Echipa, coordonată de Daniela Milculescu (Partener)
CMS asistă Frasers Group în achiziția magazinelor de articole sportive ale Hervis din România și Ungaria. Echipa, coordonată de Roxana Frățilă (Real Estate) și Mircea Moraru (Corporate ̸ M&A)
SYCLEF intră în România prin achiziția Grupului Unicool. Tranzacție asistată de Băncilă, Diaconu & Asociații și PNSA
De la conformarea GDPR, la o guvernanță complexă a datelor | Mădălina Mitel (Partener Mitel & Asociații): În proiectele complexe, întrebarea centrală nu mai este dacă există documente GDPR, ci dacă organizația poate explica fluxurile de date, poate controla persoanele împuternicite și poate reacționa coerent atunci când tehnologia schimbă modul în care sunt luate deciziile. Inteligența artificială obligă business-ul să treacă de la conformare formală la guvernanță aplicată
 
Citeste pe SeeNews Digital Network
  • BizLeader

      in curand...
  • SeeNews

    in curand...