Developing Renewables in Romania: PUZ or Pass?
17 Octombrie 2022
Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & PartnersThe practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
![]() |
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
Publicitate pe BizLawyer? |
![]() ![]() |
Articol 933 / 4571 | Următorul articol |
Publicitate pe BizLawyer? |
![]() |

Dr. Cosmin Vasile (Managing Partner ZRVP) va susține un curs de arbitraj la INPPA: “Noțiuni introductive de arbitraj comercial – un ghid practic pentru începători”, desfășurat în cinci ateliere | Înscrierile se fac până pe 7 octombrie
LegiTeam: Reff & Associates is looking for a 2 - 6 years Attorney at Law | Dispute Resolution
BOHÂLȚEANU ȘI ASOCIAȚII recrutează avocați stagiari cu 0-3 ani experienta in profesie
Kinstellar, local counsel în regiunea CEE pentru GTCR, cumpărătorul Zentiva, într-o tranzacție de 4,1 miliarde euro. Rusandra Sandu (Partner) a coordonat echipa în jurisdicția locală | Kirkland & Ellis și Freshfields au fost lead counsels
Clifford Chance Badea își consolidează practica de Corporate M&A și Real Estate prin recrutarea Flaviei Petcu-Ciurel ca Senior Associate
LegiTeam: Atorney at Law (0 - 2 years) - Dispute Resolution | Reff & Associates
„The Lawyer European Awards 2025” | Trei firme cu activitate în România concurează pentru titlu la secțiunea ”Law Firm of the Year: South Eastern Europe”: NNDKP, Popescu & Asociații și TZA, pe lista scurtă a premianților. Firma fondată de Octavian Popescu, printre finaliști și în secțiunea ”European litigation team of the year”
Oportunități, provocări și diferențe de abordare - CMS European M&A Outlook 2026 | Horea Popescu, Managing Partner CMS România: “Europa Centrală și de Est se conturează ca o surpriză pozitivă pe harta investițiilor”. Rodica Manea, Corporate Partner: “Vedem o activitate susținută pe piața locală, iar companiile românești continuă să se adapteze rapid și să valorifice oportunitățile emergente”
bpv Grigorescu Ștefănică: tranzacțiile strategice și consolidările sectoriale definesc piața de fuziuni și achiziții | 2025 aduce structuri inovatoare, distressed M&A și o redefinire a noțiunii de succes, într-o piață în care avocații devin arhitecții echilibrului între reglementări stricte și interesele investitorilor. Cătălin Grigorescu (managing partner): „Succesul în tranzacții nu se mai măsoară doar în valoare, ci în capacitatea de a le finaliza într-un mediu juridic tot mai complex”
Banking & Finance | Echipa Popovici Nițu Stoica & Asociații, coordonată de partenerul Bogdan C. Stoica, a acordat consultanță Grupului La Fântâna pentru accesarea unei finanțări sindicalizate de 70 milioane euro, menită să susțină activitatea curentă și dezvoltarea businessului
BSMP - Bohâlțeanu și Asociații a asistat UNIGEA România în contractarea unei finanțări de 30,25 milioane EUR pentru dezvoltarea unui proiect solar de referință de 85 MW în Arad. Echipă pluridisciplinară, coordonată de partenerii Daniela Milculescu și Ionuț Bohâlțeanu, într-un efort multijurisdicțional ce a reunit investitori și consultanți cheie din patru țări
Principalele aspecte pe care angajatorii trebuie să le aibă în vedere pentru a se conforma legislației privind combaterea discriminării și hărțuirii la locul de muncă | De vorbă cu Dan Dascălu (Partener) și Sonia Bălănescu (Managing Associate) - D&B David și Baias, despre prevederile legale în vigoare, combaterea acestui fenomen și modul în care poate fi diminuat riscul apariției unor litigii inițiate de salariați
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...