Developing Renewables in Romania: PUZ or Pass?
17 Octombrie 2022 Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
| |
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 964 / 4602 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
Filip & Company a asistat Global Vision Investment Fund S.A. în obținerea unei refinanțări pentru prima sa investiție în retail
Filip & Company operează în segmentul cel mai sofisticat al pieței de Capital Markets, acolo unde se proiectează emisiuni pentru stat, bănci sistemice, companii listate și emitenți antreprenoriali, toate sub presiunea unui calendar strâns și a unor standarde de conformare ridicate | De vorbă cu Olga Niță (Partener) despre direcția pieței, proiectele-reper ale anului, modul în care funcționează ”laboratorul de soluții” și mecanismele interne care permit echipei să finalizeze, la timp și în siguranță, tranzacții extrem de sofisticate
Filip & Company a asistat Grupul Banca Transilvania în finalizarea achiziției BRD SAFPP SA. Alina Stancu Bîrsan (partener) a coordonat echipa
ZRVP, desemnată din nou „Firma de Avocatură a Anului din România” la Lexology Index Awards 2025 | Dr. Cosmin Vasile (Managing Partner): Un premiu obținut doi ani la rând spune un lucru simplu: că echipa merge în direcția bună. O astfel de recunoaștere confirmă nivelul profesional atins și, în același timp, ne obligă să rămânem la fel de exigenți
Albota Law Firm își menține standardele ridicate în Real Estate cu o echipă alcătuită doar din avocați seniori, recunoscută constant în ghidurile internaționale. Practica are anvergură, ritm și disciplină, iar vizibilitatea internațională validează un mod de lucru orientat spre rezultat | De vorbă cu Oana Albota (Managing Partner) despre tendințele pieței, provocările perioadei modul în care lucrează echipa
Filip & Company a asistat Banca Transilvania în cea mai mare emisiune de obligațiuni AT1 din Europa Centrală și de Est | Echipa de proiect, coordonată de Alexandru Bîrsan (managing partner)
Balog & Stoica: Un nou jucător pe piața serviciilor juridice și o perspectivă contemporană asupra avocaturii
Lexology Index: Arbitration - 2026 | Arbitrajul românesc nu mai este doar „prezent” în clasamentele globale, ci începe să-și contureze, în mod coerent, un ecosistem. Patru avocați, printre care Cosmin Vasile (ZRVP), Crenguța Leaua (LDDP) și Luminița Popa (Popa Legal) formează nucleul de influență al practicii. ZRVP Și LDDP au cei mai mulți profesioniști în categoriile Thought Leaders și Future Leaders. România devine un „hub” credibil în arbitrajul regional
Fiscalitate ̸ Litigii Fiscale - Practica de Taxe a Kinstellar funcționează ca un „hub” integrat între drept, fiscalitate și finanțe, ce conturează un parcurs procedural previzibil, din faza de control al documentelor până la soluțiile finale ale instanței. Clienții beneficiază de pregătire proactivă, probatoriu robust și o echipă calibrată pentru litigii sofisticate | De vorbă cu Theodor Artenie (Counsel) și Raluca Botea (Counsel) despre tendințele ultimului an, prevenție, timing și modul de lucru al unei echipe recunoscute de directoarele internaționale
Țuca Zbârcea & Asociații și britanicii de la Legal 500 au lansat ediția 2025 a GC Powerlist Romania
Filip & Company a asistat Autonom Services S.A. la încheierea unui contract de facilități de credit în valoare de 300 mil. €. Ce avocați au fost în echipa de proiect
Popovici Nițu Stoica & Asociații a asistat Hexagon în achiziția Platformei CUG din Cluj, într-unul dintre cele mai mari proiecte imobiliare ale anului
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS





