Developing Renewables in Romania: PUZ or Pass?

17 Octombrie 2022   |   Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.

 
 

One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.

To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.

1.          Types of lands

The following lands qualifications are relevant for the current topic:

(i)         from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);

(ii)       from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;

(iii)      from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.

2.          General construction rule

As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.

If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),

(i)         the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;

(ii)       no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.

3.          Exception dedicated to renewable energy projects

Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:

(i)         land has fertility class III, IV and V; and

(ii)       land does not exceed 50 ha.

Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.

4.          Need of a PUZ in case of renewable projects below 50 ha

Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.

Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:

(i)            according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;

(ii)          all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);

(iii)        PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;

(iv)        if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;

(v)          generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;

(vi)        very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.

Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 951 / 4589
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
România solicită despăgubiri de 2 miliarde de euro la Curtea Internațională de Arbitraj din Londra pentru blocarea proiectului „Casa Radio” din București, dezvoltat de Plaza Centers NV | Statul și investitorii se înfruntă pe două planuri, comercial și investițional, cu seturi de remedii și probatoriu diferite, dar și cu potențiale efecte de interferență
Țuca Zbârcea & Asociații obține o soluție favorabilă într-un important litigiu de drept fiscal și vamal | Ionuț Șerban (Partener): „Este o victorie importantă pentru clientul nostru și un precedent valoros în disputele de drept vamal”
Avocații PNSA au stat alături de M Plus Croatia d.o.o, lider european în outsourcing-ul proceselor de afaceri și tehnologie, în tranzacția prin care a achiziționat Valoris Group - jucător local care deservește proiecte multilingve pentru clienți internaționali | Echipa pluridisciplinară a fost coordonată de partenerul Bogdan C. Stoica
Piața de Real Estate, radiografiată de NNDKP, firmă despre care ghidurile juridice internaționale spun că este “probabil cea mai bună din România” în această practică: industrial-logistic în viteză, office cu accent pe retenție și eficiență, rezidențial cu presiune pe preț | De vorbă cu Vlad Tănase (partener) despre dinamica pieței, apetitul investitorilor, tranzacționarea proiectelor și blocajele de pe acest segment
Biroul Kinstellar din București a fost alături de Repono AB în achiziția unui sistem de stocare pe bază de baterii în județul Argeș | Karim Nils Grueber (CEO Repono): ”Echipa Kinstellar a fost un partener excepțional pe parcursul acestei tranzacții. Expertiza lor în sectorul energetic, abordarea pragmatică și capacitatea de a răspunde rapid și eficient au fost esențiale pentru a ne ghida prin reglementările complexe ale României”
Bohâlțeanu și Asociații a asistat Microfruits SA în achiziționarea pachetului majoritar de acțiuni emise de Armătura SA, cu o echipă coordonată de Ionuț Bohâlțeanu (Managing Partner) | Proiectul a presupus o analiză juridică amplă și o coordonare atentă între toate părțile implicate
ITR World Tax 2026 | Brandurile din avocatura locală cu o activitate notabilă în domeniul taxelor urcă în top. NNDKP, CMS, PNSA, TZA, Schoenherr, Băncilă, Diaconu și Asociații, Mușat & Asociații sau Popescu & Asociații, printre cele mai bune firme locale evidențiate pe palierele de General corporate tax, Transfer pricing și Tax controversy
Baciu Partners și coordonatoarea sa au urcat pe primul loc pe podium la gala inaugurală Legal 500 - CEE Awards | Ana-Maria Baciu, după ce a primit distincția „Romania Lawyer of the Year”, iar BACIU PARTNERS a fost desemnată „CEE IP Firm of the Year”: ”Încrederea nu se câștigă printr-o conjunctură, ci prin consistență, prezență și prin convingerea că lucrurile pot fi mereu făcute altfel, în beneficiul direct al echipei și clienților. Standardul pe care îl impune este clar: să livrezi claritate și rigoare în permanență și să ai curajul să gândești diferit, înțelegând miza reală”
Legal500 a desemnat Clifford Chance Badea drept Casa de Avocatură a Anului în România în 2025 | Daniel Badea, Managing Partner: Premiile primite încununează aproape 20 de ani de excelență profesională, de-a lungul cărora ne-am consolidat poziția de lider pe piața de avocatură din România și din regiune, câștigând în paralel aprecierea întregii rețele globale Clifford Chance
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat definitiv Achiziții & Corporate| Consultanță
D&B David și Baias confirmă reziliența M&A: achiziții strategice dominante, mecanisme flexibile, grafic de lucru modelat de conformare și componenta tehnică. Echipa livrează soluții prompte în proiecte cu arhitectură complexă, aliniind interesele vânzătorilor cu obiectivele investitorilor și orchestrând integrarea post-closing | Anda Rojanschi (Partener): „Tranzacția de succes este aceea în care cele două afaceri se integrează după finalizarea deal-ului”. O regulă care devine rutină operațională prin rigoare, colaborare și coordonare interdisciplinară
Schoenherr lansează a cincea ediție a concursului de eseuri „law, sweet law‟, cu premii totale de 21.000 lei
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...