
Developing Renewables in Romania: PUZ or Pass?
17 Octombrie 2022
Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & PartnersThe practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
![]() |
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
Publicitate pe BizLawyer? |
![]() ![]() |
Articol 888 / 4526 | Următorul articol |
Publicitate pe BizLawyer? |
![]() |

Tranzacție rară pe piața românească | Cum au lucrat avocații Legal Ground în proiectul legat de achiziția unor obligațiuni ‘tokenizate’, înregistrate și tranzacționate prin sistemul blockchain. Mihai Dudoiu (Partener): ”Pe lângă aspectele comune unor proiecte de finanțare ‘clasice’, a fost necesară integrarea unei componente de fintech. Arhitectura juridică a trebuit adaptată unui cadru relativ nou și încă în formare din punct de vedere normativ”
LegiTeam: Atorney at Law (0 - 2 years) - Dispute Resolution | Reff & Associates
BizLawyer îi prezintă pe avocații care au devenit parteneri în ultimele runde de promovări | Corina Roman, avocat format în câteva firme mari, spune că a regăsit „cu drag”, la BACIU PARTNERS, aceeași preocupare pentru knowledge și dedicare față de mandatele primite de la clienți. “Nu am crezut niciodată că voi lucra într-un proiect cu sateliți, dar iată că aici am avut această ocazie. Și mi-a plăcut enorm, pentru că m-a scos din zona de confort. Acum, datorită acelei experiențe, știm mai multe și putem explora și acest tip de proiecte la nivel de echipă”
Employment | Pe parcursul ultimului an, s-a remarcat o preocupare crescută din partea angajatorilor pentru „descifrarea” obligațiilor tot mai complexe care le revin în temeiul legislației de dată recentă, spun avocații specializați în Dreptul Muncii de la PNSA. De vorbă cu Ioana Cazacu, coordonatoarea practicii, despre noutățile din legislația muncii, solicitările clienților și mandatele complexe în care a fost implicată echipa
BRD coordonează un club loan de 190 mil. € pentru NE Property BV. Avocații CMS au consiliat consorțiul bancar în această finanțare
LegiTeam: Lawyer - Corporate M&A | Reff & Associates
Cine sunt campionii pieței locale evidențiați în ultimul clasament IP Stars 2025 | Baciu Partners are cele mai multe recomandări în prima bandă din domeniul mărcilor. ZRVP și Dincă & Speciac sunt pe primul palier al performanței, urmate de Mușat & Asociații și NNDKP
CMS își consolidează echipa din România prin promovarea a șapte avocați | Horea Popescu, managing partner CMS România: ”Aceste promovări reflectă nu doar calitatea muncii lor, ci și energia și dedicarea cu care aduc rezultate remarcabile clienților noștri și ne poziționează perfect pentru a ne continua creșterea și dezvoltarea competențelor”
LegiTeam | Mitel & Asociații recrutează avocat cu experiență (Litigii și Soluționare a Disputelor)
Țuca Zbârcea & Asociații câștigă pentru Silcotub un litigiu major privind recalcularea prețului energiei electrice în lumina Ordonanței de urgență nr. 27 ̸ 2022
Filip & Company a asistat Banca Transilvania în prima sa emisiune de obligațiuni sustenabile în lei în valoare de 1,5 miliarde de lei. Alexandru Bîrsan (managing partener) a coordonat echipa
Women Lawyers | Din vorbă în vorbă cu Andreea Mihalache, Partener în cadrul firmei Popescu & Asociații, profesionist reputat, cu aproape 30 de ani de experiență ca avocat litigant la cel mai înalt nivel: ”Dincolo de oportunitatea de a lucra la dosare complexe, am și sprijinul unei echipe unite, ceea ce face ca fiecare provocare să fie o oportunitate de învățare și evoluție profesională”
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...