Developing Renewables in Romania: PUZ or Pass?
17 Octombrie 2022
Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & PartnersThe practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
Publicitate pe BizLawyer? |
Articol 772 / 4411 | Următorul articol |
Publicitate pe BizLawyer? |
Refinitiv Legal Advisers - Full Year 2024 | La nivel global, piața fuziunilor și achizițiilor a crescut cu 10% anul trecut, iar pe continentul European avansul a fost de 22%. CMS, în Top 10 consultanți juridici care au asistat cele mai multe tranzacții de M&A la nivel global, Clifford Chance se remarcă pe ”bătrânul continent”, iar Schoenher în Estul Europei, regiune în care Filip & Company a intrat în Top 25
Filip & Company a asistat PayPoint Services în contractarea unui credit sindicalizat de la UniCredit Bank și BERD | Alexandru Bîrsan (partener) şi Camelia Ianțuc (senior associate) au coordonat echipa de proiect
Iablonschi & Asociații se alătură rețelei Marcalliance, care își consolidează astfel rețeaua globală și prezența în Europa de Est | Dorothée De Bernis (Președinte Marcalliance): ”Ne bazăm în România pe o echipă juridică de încredere”
Hațegan Attorneys, firmă de avocatură de tip butique cu sediul la Timișoara, își consolidează practica de Banking & Finance prin cooptarea unui profesionist cu experiență în corporate banking pe poziția de counsel
Arbitrajul ICSID cerut de 15 firme și 28 de persoane fizice din 7 țări, care care cer compensații pentru tratamentul aplicat de autoritățile române, a ajuns la final | Statul român așteaptă decizia, după ce Tribunalul a declarat închisă procedura în litigiul în care pretențiile se ridică la cca. 213 milioane USD. Ce onorarii au fost plătite firmelor de avocați care au asigurat apărarea
Filip & Company asistă Credit Europe Bank România în fuziunea transfrontalieră cu Credit Europe Bank NV | Partenerele Alexandra Manciulea și Eliza Baias au coordonat echipa. Modificarea semnificativă a cadrului legislativ pe parcursul pregătirii acestei fuziuni a adăugat complexitate proiectului, spun avocații
Primele mișcări pe piața muncii din avocatură | Băncilă Diaconu & Asociații recrutează un partener de la Stratulat Albulescu și un fost Head of Legal din sectorul bancar se alătură firmei Rizoiu & Asociații
Edward Sukyas pierde arbitrajul cu statul român și trebuie să plătească peste o jumătate de milion de euro - cheltuieli arbitrale și onorarii plătite avocaților care au apărat România. Litigiul cu Jack Sukyas merge mai departe, modul de alocare a cheltuielilor de arbitraj fiind decis într-o etapă ulterioară a procedurii | Cât au însumat onorariile primite de avocații români aflați de-o parte și alta a baricadei și ce sume au încasat arbitrii
Cum a fost anul 2024 pentru Duțescu & Partners: poziționare în topul internațional al firmelor de avocați evidențiate în practica de Capital Markets, lansarea practicii de drept islamic și multe victorii obținute pentru clienți | De vorbă cu Dr. Cristian Duțescu (partener fondator) și Casiana Dușa (partener) despre parcurs, proiecte și realizări
Precedent important obținut de RTPR pentru Premier Energy Furnizare în materia teoriei impreviziunii. Despăgubiri de aproximativ 4 milioane EUR și dobânzi legale penalizatoare, ca urmare a neexecutării unui contract de furnizare de energie încheiat pe piața PCCB-BC. Alexandru Stănoiu (Counsel) și Ana Popa (Senior Associate), în echipa coordonată de Valentin Berea (Partener)
Bulboacă și Asociații facilitează atragerea de finanțare, la final de an, pentru o companie românească de succes din industria panificației
Pentru echipa de insolvență de la Țuca Zbârcea & Asociații, anul 2024 s-a caracterizat printr-o intensificare a volumului de muncă, cu mandate noi care s-au adăugat unui portofoliu existent bogat. Cele mai multe proiecte au avut complexitate și miză ridicată, necesitând extinderea echipelor implicate și un volum mai intens de activitate | De vorbă cu Cătălina Mihăilescu (Partener) despre activitatea departamentului și planurile de viitor
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...