Developing Renewables in Romania: PUZ or Pass?
17 Octombrie 2022 Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
| |
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 957 / 4595 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
PNSA, consultanții Five Elms Capital în runda de finanţare serie B a companiei Digitail Inc. | Echipă pluridisciplinară extinsă, coordonată de Florian Nițu (Partener M&A) și Diana Dobra (Managing Associate)
VIDEO-INTERVIURI ESENȚIALE | Horea Popescu, Managing Partner CMS Romania și Head of CEE Corporate M&A: De când coordonez practica de fuziuni și achiziții în CEE, este pentru prima dată când numărul tranzacțiilor din România este cel mai mare din regiune după primele nouă luni. A fost un an interesant din perspectiva private equity, însă investitorii strategici rămân în continuare cei de bază. Toate ariile de practică au fost foarte ocupate, dar finanțările și departamentul de Banking, cu mandate ce însumează 3 miliarde euro, ”poartă coroana” anul acesta
Cum arată, din interior, practica de Concurență de la 360Competition într-un an cu FDI intens, investigații tot mai tehnice și o presiune procedurală care schimbă regulile jocului | De vorba cu Adrian Șter (Managing Partner) despre axele de lucru care definesc practica, evaluarea corectă a riscului şi „linia de apărare” oferită clienţilor. Modelul senior-led bazat pe echipe compacte, rapiditate în decizii şi claritate în recomandări, arată de ce un boutique specializat e chemat frecvent acolo unde mandatele devin prea complicate pentru abordări standard
‘Leading lawyers’ in Romania | RTPR, NNDKP, CMS, TZA și PNSA au cei mai mulți avocaţi recomandaţi de IFLR 1000, ediția 2025. Ce firme sunt recomandate în practicile de M&A, Banking & Finance, Capital markets și Project development
Practica de Concurență de la Băncilă, Diaconu și Asociații își confirmă maturitatea prin claritate și execuție disciplinată, luciditate tactică și robustețe în decizie | De vorbă cu Claudia Grosu (Managing Associate) despre modul de lucru al unei echipe care anticipează, ordonează pașii esențiali și finalizează impecabil mandatele dificile
Într-un an cu investigații mai tehnice și presiune pe termene, DLA Piper România așază practica de Concurență pe trei piloni - oameni, metodă, ritm, astfel încât proiectarea strategiilor, controlul probelor și continuitatea între faze să producă cele mai bune rezultate | De vorbă cu membrii unei echipe sudate, condusă de lideri cu experiență și antrenată pe industrii sensibile, despre prudență juridică și curaj tactic, cooperare internă și rigoare probatorie, bazate pe înțelegerea fină a mediului de business și utilizarea tehnologiei ca multiplicator de acuratețe
CMS, alături de Buildcom EOOD la achiziția Argus în România. Echipă pluridisciplinară, cu Rodica Manea (Corporate M&A) și Cristina Reichmann în prim plan
Filip & Company a acordat asistență juridică companiei Instant Factoring în structurarea și implementarea unui parteneriat transfrontalier de securitizare în valoare de 30 de milioane EUR cu un fond din Luxemburg
Schoenherr a asistat fondatorii Calla Oradea în vânzarea unei participații majoritare către Integral Capital Group I Echipa, coordonată de Mădălina Neagu (partner)
Mușat & Asociații anunță cooptarea fostei președinte a Curții Supreme, Corina Corbu, în poziția de Partener Coordonator al Departamentului de Litigii | Gheorghe Mușat, Senior Partner: ”Este un mare câștig pentru firmă, pentru avocații firmei, pentru clienții firmei”
Filip & Company a oferit asistență juridică în legătură cu o nouă emisiune de obligațiuni corporative garantate de către Agroserv Măriuța, în valoare de 3 mil. €
Kinstellar asistă Integral Capital Group în achiziția unei participații majoritare la clinica de fertilizare in vitro Calla, prin subsidiara sa Embryos
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS